Testing is run at appropriate times without human involvement and reports are direct and concise.

User Story

As a person responsible for software quality and correctness for my project, I want code regularly tested so that regressions are guarded against and new code is tested against itself and other commits the developer might not have had.

Card(s)

Variant A: How will I measure when I have achieved my desired result?

Stage Description
0 Regression and unit tests exist but are only run when requested by a developer.
1 Tests are run automatically according to the teams policy.
2 Test reports are generated as needed and archived.
3 Archived reports are posted to appropriate maintainers.
4 Code may not be integrated if automated tests fail.
5 A mechanism and policy exists to integrate code without passing tests in rare circumstances.

Variant B: What are the steps (tasks) I need to accomplish to achieve my goal?

Stage Description
0 No CI testing adopted.
1 Team adopts a CI method.
2 Team adopts a standard time to run specific sets of tests.
3 Team develops triggers and scripts to run the tests.
4 Team develops methods to prohibit failing code/tests from being integrated.
5 Team establishes policy to bypass required testing in the rare cases it is appropriate.

Comments

Acknowledgement